Construction of facilities for the APEC summit is on schedule 
Work on building a bridge across the Golden Horn Bay are on schedule. At the end of September to finalize the kotlovana the construction of the tunnel at the cable car, will begin its concreting. 
The bridge over the Golden Horn bay erected in a federal sub «Development of Vladivostok as a center of international cooperation in the Asia-Pacific countries». Target plans to build six stages. Open direct communication between the central part of the city and the Cape Churkin anticipated in 2011. 
- All construction work is on schedule - assured the director genpodryadnoy organization Victor ridge. 
Concreting chetyrehpolosnogo road tunnel should take about three months. In parallel with these works will begin construction of one of the pillars of the bridge - pilona a height of 226 meters. Location for installation design is ready, for which workers had to otsypat about 60 thousand cubic meters of rock. 
«Twin brother» of the buildings will be constructed on the opposite side of the bay - on the territory of Pervomaisky dockyard. 
As reported in the department of roads Primorsky Krai, in 2008, the new facility will be sent to 3,2 billion rubles, including 402.9 million from the provincial budget. 
At the turn - other facilities being built in preparation of Vladivostok for the APEC summit. Already established general contractor to build a second bridge, which, through the Bosporus Strait linking East Russian island with the mainland. This bridge that is about three miles scheduled for completion in spring 2012. It will be unique - sites such difficulties in Russia have not yet been built. 
Both the bridge will link between a new road. Her project of the Bay Patrokl to bridge across the Golden Horn bay design became the winner specialists Institute «In-morgrazhdanproekt». The full project estimate documentation will be ready in December 2009. 
The bridge over the Golden Horn - the most notable building in Vladivostok.
At six months earlier than planned to complete the project roads New Town - Peninsula De-Friz - Sedanka. They are already engaged in Khabarovsk branch of the Moscow Institute «GiprodorNII». This track is designed as a fast, linking the airport and the center of Seaside capital. To do this through Amur Bay will be built chetyrehkilometrovaya pier. The main building is promoted in 2010-2011. 
Total for the summit will be built 96 sites, 42 of which receive federal funding. In particular, provides for the modernization of the airport «Vladivostok», construction of transport interchanges between the airport and the regional center, Opera and Ballet Theater, congress center, several hotels. Planned upgrading of public infrastructure capital of the province. Particular attention in the federal program is given to the development of transport complex of Primorye.